Bench Setup and Operation 3-21
SG4000 Installation and Operation Manual
10
Verify that the green LED (ON), located on the top panel of each SG4-R/*, is illuminated to
confirm enable status.
11 Using a voltmeter, test the optical input power to the receivers.
Figure 4-2 illustrates the optical power test point on the top panel of the SG4-R/* receiver.
The scaled voltage at this test point is 1.0 V/mW.
12 Measure the RF output level at the receiver’s 20 dB RF test point using an RF meter.
For 0 dBm (1.0 mW) input, the receiver output level is approximately 26 dBmV at 870 MHz.
Other output levels are presented in Table 4-2.
13 Select the appropriate JXP-* pad from Table 2-2. Insert it into each receiver’s pad facility.
14 Check the 20 dB RF test point on the SG4-RF module connected to each receiver.
15 Determine how much output (excess or shortage) is present at each SG4-RF module. If
necessary, install the appropriate JXP pad at the output pad location.
Unbalanced padding can degrade isolation performance. Ensure that equivalent optical power
levels are present on each receiver if possible.